Freshfields, Fairy Lane - Battery Storage
REPD record 12694. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 99.9 MW
- Status
- Under Construction
- Operator
- STOR Power Utilities Limited
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Trafford
- Planning reference
- 109463/FUL/22
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-01-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-10-25: Planning Application Submitted
- 2023-03-20: Planning Permission Granted
- 2026-01-01: Under Construction
- 2026-03-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12694. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.