slava.energy: UK renewable energy projects
National Grid Electricity Substation, Capenhurst Lane - Battery Storage
REPD record 12725. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 100 MW
- Status
- Operational
- Operator
- Zenobe Energy Limited
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Cheshire West and Chester
- Planning reference
- 20/03681/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-10-07: Planning Application Submitted
- 2021-02-01: Planning Permission Granted
- 2021-06-01: Planning Permission Expired
- 2023-02-11: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12725. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.