slava.energy: UK renewable energy projects
Halfway House, Lincoln Hill - Energy Storage
REPD record 12841. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 2.5 MW
- Status
- Planning Permission Granted
- Operator
- Humshaugh Net Zero
- County
- Northumberland
- Region
- North East
- Country
- England
- Planning authority
- Northumberland
- Planning reference
- 22/03978/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-12-05: Planning Application Submitted
- 2023-07-14: Planning Permission Granted
- 2026-07-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12841. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.