Whistle Mead Solar Farm, Little Chalfield - Solar Farm
REPD record 12884. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 21.14 MW
- Status
- Planning Permission Refused
- Operator
- Private Developer
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- PL/2023/01914
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-03-06: Planning Application Submitted
- 2026-04-23: Planning Permission Refused