Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.26 MW
- Status
- Planning Permission Granted
- Operator
- Games Workshop
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Nottingham
- Planning reference
- 22/02408/PATPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-12-15: Planning Application Submitted
- 2023-02-02: Planning Permission Granted