REPD record 1299. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.6 MW
- Status
- Operational
- Operator
- Lark Energy
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- North Norfolk
- Planning reference
- PF/13/0960
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-08-19: Planning Application Submitted
- 2013-11-15: Planning Permission Granted
- 2014-02-01: Under Construction
- 2014-07-03: Operational
- 2019-11-15: Planning Permission Expired