slava.energy: UK renewable energy projects
North James Cropper, Garnett Bridge Road - Solar Array
REPD record 13024. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3 MW
- Status
- Planning Permission Granted
- Operator
- Ellergreen Hydro
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Westmorland and Furness
- Planning reference
- SL/2022/1159
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-01-03: Planning Application Submitted
- 2024-01-17: Planning Permission Granted
- 2027-01-17: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13024. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.