slava.energy: UK renewable energy projects
NEWNTON DAIRY FARM
REPD record 1304. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 7.2 MW
- Status
- Operational
- Operator
- Anesco
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 13/01561/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-04-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-09-10: Planning Permission Expired
- 2013-06-12: Planning Application Submitted
- 2013-09-10: Planning Permission Granted
- 2014-03-19: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1304. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.