Moorhouse Farm, Moorhouse Lane - Solar Park
REPD record 13054. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.81 MW
- Status
- Under Construction
- Operator
- Cabot Park Solar Limited
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Bristol, City of
- Planning reference
- 22/05849/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-01-03: Planning Application Submitted
- 2024-04-30: Planning Permission Granted
- 2025-11-01: Under Construction
- 2027-04-30: Planning Permission Expired
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13054. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.