Pierces Farm
REPD record 1306. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.7 MW
- Status
- Operational
- Operator
- NextEnergy Capital
- County
- Berkshire
- Region
- South East
- Country
- England
- Planning authority
- West Berkshire
- Planning reference
- 13/03187/COMIND
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-03-19: Planning Permission Expired
- 2013-12-23: Planning Application Submitted
- 2014-03-19: Planning Permission Granted
- 2014-10-16: Under Construction
- 2015-03-15: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1306. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.