Westbury (Closed) Landfill Site
REPD record 1314. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.5 MW
- Status
- Operational
- Operator
- Viridor
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 13/01962/WCM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-17: Planning Application Submitted
- 2013-10-21: Planning Permission Granted
- 2014-05-01: Under Construction
- 2014-08-05: Operational
- 2017-10-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1314. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.