East Gormack Farm - Battery storage
REPD record 13150. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Planning Permission Granted
- Operator
- Lornty Farms
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 23/00012/FLL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-06-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-01-23: Planning Application Submitted
- 2023-05-31: Planning Permission Granted
- 2026-03-31: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13150. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.