slava.energy: UK renewable energy projects
Harbro, Birkhill Commercial Park - Solar Panels
REPD record 13178. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.39 MW
- Status
- Planning Permission Granted
- Operator
- Harbro limited
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- South Lanarkshire
- Planning reference
- P/23/0058
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-09-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-01-30: Planning Application Submitted
- 2023-08-24: Planning Permission Granted
- 2026-08-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13178. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.