Grain Harvesters Ltd
REPD record 1320. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1 MW
- Status
- Operational
- Operator
- Grain Harvesters Ltd
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Dover
- Planning reference
- 13/01006
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-01-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-12-05: Planning Application Submitted
- 2014-03-06: Planning Permission Granted
- 2014-09-21: Under Construction
- 2014-12-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1320. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.