Carrog Ganol, Rhosgoch - Battery Energy Storage System
REPD record 13217. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 300 MW
- Status
- Planning Permission Granted
- Operator
- Boom Developments Limited
- County
- Isle of Anglesey
- Region
- Wales
- Country
- Wales
- Planning authority
- Isle of Anglesey
- Planning reference
- FPL/2023/218
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-08-15: Planning Application Submitted
- 2024-09-26: Planning Permission Granted
- 2029-09-26: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13217. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.