slava.energy: UK renewable energy projects

Merchiston Industrial Estate, Smith Street - Battery Storage

REPD record 13225. Status: Under Construction.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
43 MW
Status
Under Construction
Operator
Falkirk Power Limited
County
Falkirk
Region
Scotland
Country
Scotland
Planning authority
Falkirk
Planning reference
P/23/0046/FUL
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2025-12-02

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13225. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.