slava.energy: UK renewable energy projects
Wiltshire College, Lackham - Solar Panels
REPD record 13395. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.32 MW
- Status
- Planning Permission Granted
- Operator
- Wessex Energy Solutions
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- PL/2022/09178
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-04-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-01-20: Planning Application Submitted
- 2023-04-12: Planning Permission Granted
- 2026-04-12: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13395. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.