slava.energy: UK renewable energy projects

PONTRILAS BIOMASS POWER PLANT

REPD record 134. Status: Abandoned.

Facts

As published by REPD, release Q3 2026.

Technology
Biomass (dedicated)
Capacity
10 MW
Status
Abandoned
Operator
James Barr Ltd
County
Hereford and Worcester
Region
West Midlands
Country
England
Planning authority
Herefordshire, County of
Planning reference
DCSW2006/3693/N
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2013-04-24

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 134. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.