slava.energy: UK renewable energy projects
Beaford Brook Solar Park
REPD record 1346. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.2 MW
- Status
- Operational
- Operator
- Wessex Solar Energy
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Torridge
- Planning reference
- 1/0571/2012/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-06-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-07-23: Planning Application Submitted
- 2012-12-07: Planning Permission Granted
- 2013-06-03: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1346. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.