Kemsley Energy Park Battery Storage
REPD record 13489. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 120 MW
- Status
- Planning Permission Granted
- Operator
- FPC Electric Land Limited
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Swale
- Planning reference
- 23/500771/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-03-16: Planning Application Submitted
- 2024-09-30: Planning Permission Granted
- 2027-09-30: Planning Permission Expired