Lentons Lane Solar Farm
REPD record 13503. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 30 MW
- Status
- Planning Permission Refused
- Operator
- Coventry City Council
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Coventry
- Planning reference
- PL/2023/0001062/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-04-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-05-30: Planning Application Submitted
- 2024-03-21: Planning Permission Refused