First Bus, Blue Business Depot- Solar Panels
REPD record 13505. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.17 MW
- Status
- Planning Permission Granted
- Operator
- First Bus
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- Great Yarmouth
- Planning reference
- 06/23/0100/PAD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-06-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-02-03: Planning Application Submitted
- 2023-05-11: Planning Permission Granted
- 2026-05-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13505. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.