slava.energy: UK renewable energy projects
Pont Andrew Solar Farm
REPD record 1356. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.5 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Dyfed
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- S/24069
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-03-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-11-29: Planning Application Submitted
- 2011-04-22: Planning Permission Granted
- 2012-07-31: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1356. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.