Tenax Road - Renewable Energy Biomass Plant
REPD record 136. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 3 MW
- Status
- Abandoned
- Operator
- Fluid Leader Plc
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Trafford
- Planning reference
- H/70807
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-06-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-06-29: Planning Permission Expired
- 2009-01-21: Planning Application Submitted
- 2009-06-29: Planning Permission Granted
Open this area on the map