slava.energy: UK renewable energy projects

Southlands Solar Farm & Battery Storage

REPD record 13677. Status: Appeal Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
24.6 MW
Status
Appeal Granted
Operator
Enso Green Holdings Limited & Cero Generation
County
Essex
Region
Eastern
Country
England
Planning authority
Chelmsford
Planning reference
23/00532/FUL
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2025-01-13

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13677. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.