Persley Croft - Battery Storage
REPD record 13684. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Granted
- Operator
- RE Projects Development
- County
- Aberdeenshire
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeen City
- Planning reference
- 231134/DPP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-09-12: Planning Application Submitted
- 2024-08-29: Planning Permission Granted
- 2027-08-29: Planning Permission Expired