Loggans Roundabout, Loggans Road - Solar Farm
REPD record 13700. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 2.5 MW
- Status
- Planning Permission Granted
- Operator
- Bauer Group
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA24/02723
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-03-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-04-23: Planning Application Submitted
- 2025-02-17: Planning Permission Granted
- 2028-02-17: Planning Permission Expired