Seashore Holiday Park, North Drive - Solar Panels
REPD record 13721. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.52 MW
- Status
- Planning Permission Granted
- Operator
- Bourne Leisure Limited
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- Great Yarmouth
- Planning reference
- 06/23/0169/PAD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-07-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-04-12: Planning Application Submitted
- 2023-06-07: Planning Permission Granted
- 2026-06-07: Planning Permission Expired