Fair Park Solar Farm
REPD record 13760. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Appeal Granted
- Operator
- Downing Renewable Developments Llp
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA23/02629
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-04-17: Planning Application Submitted
- 2024-11-26: Planning Permission Refused
- 2025-05-13: Appeal Lodged
- 2025-10-16: Appeal Granted
- 2025-10-16: Planning Permission Granted
- 2028-10-16: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13760. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.