Burbage House - Solar Array
REPD record 13766. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Planning Permission Granted
- Operator
- Burbage Farms Limited
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Hinckley and Bosworth
- Planning reference
- 23/00378/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-08-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-04-18: Planning Application Submitted
- 2023-07-13: Planning Permission Granted