Bolney - Battery Storage
REPD record 13880. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 200 MW
- Status
- Planning Permission Granted
- Operator
- Elements Green
- County
- West Sussex
- Region
- South East
- Country
- England
- Planning authority
- Horsham
- Planning reference
- DM/21/2276
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-04-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-06-22: Planning Application Submitted
- 2024-09-05: Planning Permission Granted
- 2027-09-05: Planning Permission Expired