slava.energy: UK renewable energy projects
Bedworth Lane, Coolliery Wood - Solar Farm & Battery Storage
REPD record 13948. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 5 MW
- Status
- Revised
- Operator
- Sirius Environmental Limited
- County
- Warwickshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Nuneaton and Bedworth
- Planning reference
- 39547
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-06-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-04-05: Planning Application Submitted
- 2023-07-24: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13948. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.