slava.energy: UK renewable energy projects
Liscombe Business Park - Ground Mounted Solar Array
REPD record 13965. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.27 MW
- Status
- Planning Permission Granted
- Operator
- Liscombe Park Limited
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 23/01505/APP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-05-15: Planning Application Submitted
- 2024-02-06: Planning Permission Granted
- 2027-02-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13965. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.