slava.energy: UK renewable energy projects
Goyt Hall Farm, Goyt Valley Footpath - Battery Energy Storage
REPD record 13985. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 40 MW
- Status
- Planning Permission Granted
- Operator
- Queequeg Renewables Limited
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Stockport
- Planning reference
- DC/090340
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-09-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-12-01: Planning Application Submitted
- 2024-08-23: Planning Permission Granted
- 2027-08-23: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 13985. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.