slava.energy: UK renewable energy projects
Chilton Energy Plant
REPD record 14. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 18 MW
- Status
- Operational
- Operator
- Dalkia
- County
- County Durham
- Region
- North East
- Country
- England
- Planning authority
- County Durham
- Planning reference
- 7/2008/0522/DM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2012-04-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-11-24: Planning Permission Expired
- 2008-09-17: Planning Application Submitted
- 2009-11-24: Planning Permission Granted
- 2010-03-01: Under Construction
- 2012-03-12: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.