slava.energy: UK renewable energy projects
The Balk, Almholme - Energy Storage System
REPD record 14061. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 1025 MW
- Status
- Planning Permission Granted
- Operator
- Innova Renewables
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Doncaster
- Planning reference
- 23/02482/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-10-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-11-29: Planning Application Submitted
- 2024-10-14: Planning Permission Granted
- 2029-10-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14061. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.