Thornton And Ross, Manchester Road - Solar Photovoltaic Panels
REPD record 14075. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.51 MW
- Status
- Planning Permission Granted
- Operator
- Thornton and Ross Limited
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Kirklees
- Planning reference
- 2023/CLASS J/91579/W
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-06-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-06-01: Planning Application Submitted
- 2023-07-25: Planning Permission Granted
- 2026-07-25: Planning Permission Expired