slava.energy: UK renewable energy projects
Chimmens Solar Farm
REPD record 14077. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Planning Permission Refused
- Operator
- RES Limited
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Sevenoaks
- Planning reference
- 23/03181/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-08-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-12-19: Planning Application Submitted
- 2024-07-23: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14077. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.