slava.energy: UK renewable energy projects
Green Farm (Wix Manningtree)
REPD record 1417. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 7 MW
- Status
- Revised
- Operator
- Hive Energy
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Tendring
- Planning reference
- 13/01210/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-03-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-11-08: Planning Application Submitted
- 2014-02-07: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1417. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.