slava.energy: UK renewable energy projects
Workstown Industrial Estate, Princes Road - Solar Panels
REPD record 14189. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Planning Permission Granted
- Operator
- Direct Wholesale Foods
- County
- London
- Region
- London
- Country
- England
- Planning authority
- Enfield
- Planning reference
- 23/01834/PRV
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-08-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-06-15: Planning Application Submitted
- 2023-08-18: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14189. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.