- Technology
- Battery
- Capacity
- 100 MW
- Status
- Planning Permission Granted
- Operator
- Green Switch Capital Limited
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- ECU00004823
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-11-11: Planning Application Submitted
- 2026-07-30: Planning Permission Granted
- 2031-07-30: Planning Permission Expired