Blair Castle Caravan Park, Blair Atholl - Solar Farm
REPD record 14202. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.16 MW
- Status
- Operational
- Operator
- Atholl Estates
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 23/00716/FLL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-02-01: Under Construction
- 2023-05-01: Operational
- 2023-06-12: Planning Application Submitted
- 2023-07-24: Planning Permission Expired
- 2023-07-25: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14202. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.