Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.86 MW
- Status
- Operational
- Operator
- Scottish Water
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- North Lanarkshire
- Planning reference
- 24/00356/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-10-12
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-05-17: Planning Permission Expired
- 2024-04-22: Planning Application Submitted
- 2024-05-17: Planning Permission Granted
- 2025-01-01: Under Construction
- 2026-09-30: Operational