Parker Hannifin Manufacturing - Solar Panels
REPD record 14249. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.08 MW
- Status
- Planning Permission Granted
- Operator
- Parker Hannifin Manufacturing
- County
- Tyne And Wear
- Region
- North East
- Country
- England
- Planning authority
- Gateshead
- Planning reference
- DC/23/00390/NPA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-08-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-06-21: Planning Application Submitted
- 2023-08-10: Planning Permission Granted