slava.energy: UK renewable energy projects
Kellygreen Farm
REPD record 1428. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4 MW
- Status
- Operational
- Operator
- INRG Solar
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA13/07973
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-06-23: Planning Permission Expired
- 2013-09-02: Planning Application Submitted
- 2013-11-22: Planning Permission Refused
- 2014-01-30: Appeal Lodged
- 2014-06-23: Appeal Granted
- 2014-06-23: Planning Permission Granted
- 2016-02-05: Under Construction
- 2016-03-30: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1428. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.