Grove Farm (solar)
REPD record 1429. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.5 MW
- Status
- Operational
- Operator
- Juwi Renewable Energies
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 41/13/0004
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-12-03: Planning Application Submitted
- 2014-02-27: Planning Permission Granted
- 2015-01-05: Under Construction
- 2015-03-24: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1429. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.