Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Refused
- Operator
- Whirlwind Renewables
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 23/03113/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-07-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-06-29: Planning Application Submitted
- 2024-12-17: Planning Permission Refused