Nucleus, Central Way - Solar Panels
REPD record 14409. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.32 MW
- Status
- Planning Permission Granted
- Operator
- Boreal UK Industrial 2 Unit Trust
- County
- London
- Region
- London
- Country
- England
- Planning authority
- Brent
- Planning reference
- 23/2272
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-08-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-07-03: Planning Application Submitted
- 2023-08-25: Planning Permission Granted
- 2026-08-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14409. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.