Castle Road, Eurolink - Solar Panels
REPD record 14610. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.46 MW
- Status
- Planning Permission Granted
- Operator
- Cross & Wells Limited
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Swale
- Planning reference
- 23/503167/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-09-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-08-02: Planning Application Submitted
- 2023-09-26: Planning Permission Granted
- 2026-09-26: Planning Permission Expired