Marley Thatch Solar Farm
REPD record 1467. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.3 MW
- Status
- Operational
- Operator
- TGC Renewables
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- South Hams
- Planning reference
- 39_45/0706/12/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-04-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-03-29: Planning Application Submitted
- 2012-06-28: Planning Permission Granted
- 2013-01-28: Under Construction
- 2013-03-31: Operational
- 2019-06-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1467. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.